New Meeting
Dec 14, 2020 04:30 AM - Dec 14, 2020 05:00 AM
Theo Bardis
Status: Meeting Successfully Completed
Description: Site visit. still down 5 levels in basement. Transfer slab should be around mid Feb. Shop drawing meeting mid Jan 21

Call scheduled with Charbel Youssef
Sep 17, 2020 03:30 AM
Theo Bardis
Contact Name:

Status: Cancelled
Descriptions:

Outgoing call to Charbel Youssef
Aug 19, 2020 07:00 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: Just finished piling. will be looking at scaff in the next 1-2 months. He stated he provided my info to his cousin Michael who will contact me for a quote

Follow Up
Aug 18, 2020 07:00 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: Called and left a voicemail.

Meeting
Jul 13, 2020 05:30 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: Piling at the moment. Job will be 5 basements and 96 units. scaff will be looked at in about 6-8 weeks. basement stairs to be required late October/nov. Scaff probably early next year. Kemps Creek done their last job. Will be reaching out to 3 scaff companies he reckons