FSS4687- STARGATE Sep 13, 2023
Yousif Yousif
Closed Time: 2023-09-12T05:56:32+05:30
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


Book Discovery Meeting Sep 13, 2023
Theo Bardis
Closed Time: 2024-03-28 10:49:11AM
Status: Completed
Estimating Task Type: None
Description: A builder has been appointed to this project. It's time to book in a discovery meeting!

FSS4687- STARGATE Apr 02, 2024
Yousif Yousif
Closed Time: 2024-04-03 08:51:05AM
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


FSS4687- STARGATE Apr 03, 2024
Randa Alrifai
Closed Time: 2024-04-20 02:15:43PM
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


FSS4687- STARGATE Apr 30, 2024
Yousif Yousif
Closed Time: 2024-05-06 02:33:48PM
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


FSS4687- STARGATE May 21, 2024
Yousif Yousif
Closed Time: 2024-05-27 02:05:09PM
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


FSS4687- STARGATE Feb 19, 2025
Yousif Yousif
Closed Time: 2025-02-21 03:57:11PM
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


New Meeting
Mar 20, 2024 04:00 AM - Mar 20, 2024 05:00 AM
Theo Bardis
Status: Meeting Successfully Completed
Description: Will be needing stairs in the whole in about 6 months when they hit the bottom. Perimeter to start 1st qtr 25. Discussed original scope and changes that are required. Formscaff, FSS and maybe on other quoting. Will meet with him after easter to run through the project

Outgoing call to Vernon Houston
Apr 08, 2025 03:30 PM
Contact Name:

Status: Completed
Descriptions: George called me and he stated formscaff has based out and is using ringlock system

Outgoing call to Vernon Houston
Mar 27, 2025 10:30 AM
Contact Name:

Status: Completed
Descriptions: called Michael and got voicemail as per usual

Outgoing call to Vernon Houston
Mar 26, 2025 10:30 AM
Contact Name:

Status: Completed
Descriptions: Sent michael an email and have not heard back

Outgoing call to Vernon Houston
Mar 03, 2025 01:30 PM
Contact Name:

Status: Completed
Descriptions: Called Michale and got voicemail

Outgoing call to Vernon Houston
Feb 10, 2025 05:00 PM
Contact Name:

Status: Completed
Descriptions: spoke with George,he said Michael, the director and formscaff were walking around the site on Friday

Outgoing call to Vernon Houston
Feb 10, 2025 05:00 PM
Contact Name:

Status: Completed
Descriptions: Called and text Michael and got nothing. Will email him tomorrow.

Outgoing call to Vernon Houston
Feb 03, 2025 10:30 AM
Contact Name:

Status: Completed
Descriptions: Called and got voicemail

Outgoing call to Vernon Houston
Feb 03, 2025 10:30 AM
Contact Name:

Status: Completed
Descriptions: Sent michael a text regarding the scaff package

Outgoing call to Vernon Houston
Jan 08, 2025 09:30 AM
Contact Name:

Status: Completed
Descriptions: spoke with Michael and he stated scaff pacakge to be looked at early Feb and be awarded arouund end of Feb. Scaff on site to be required mid to late March, pending

Outgoing call to Vernon Houston
Oct 21, 2024 09:30 AM
Contact Name:

Status: Completed
Descriptions: Michael stated they are doing detailed bulk at the moment. Looking at other trades like electrical and formwork. Reckons they will look at scaff late November/early december. may be awarded before the end of the year

Outgoing call to Vernon Houston
Oct 08, 2024 12:00 PM
Contact Name:

Status: Completed
Descriptions: George theSM told me he has not spoken to the team about updated SOW

Outgoing call to Vernon Houston
Sep 19, 2024 05:30 PM
Contact Name:

Status: Completed
Descriptions: Hi Theo, Sorry I missed your call. Not update as of yet, sorry just been prioritising other items. Will be in touch soon!

Outgoing call to Vernon Houston
Sep 19, 2024 01:00 PM
Contact Name:

Status: Completed
Descriptions: Called Michael and got voicemail. Sent him email as welll

Outgoing call to Vernon Houston
Sep 17, 2024 05:00 PM
Contact Name:

Status: Completed
Descriptions: Called Michael and got voicemail

Outgoing call to Vernon Houston
Aug 23, 2024 11:00 AM
Contact Name:

Status: Completed
Descriptions: Michael stated they want the loading bays in the curved balcony area dur to access into building and space constraints. Will speak with Ranji to get his views

Call scheduled with Vernon Houston
Apr 15, 2024 03:00 PM
Theo Bardis
Contact Name:

Status: Completed
Descriptions:

Outgoing call to Vernon Houston
Mar 13, 2024 07:56 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: In piling stage. Should start the dig in the next couple of weeks. Digging to take 6 months and then 4 months to come out of the ground. Starting with Ramp. Stairs in the whole mid year or so. Updated scaff package to come out around the end of the month vernon stated

Call scheduled with Vernon Houston
Mar 13, 2024 02:00 PM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Outgoing call to Vernon Houston
Jan 19, 2024 05:07 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: have another month of piling then about 4 months in the hole. Want to do an inclusive package for stairs and main package. Will need stairs end of march/April. Will be looking at scaff package around end of Feb

Outgoing call to Vernon Houston
Jan 16, 2024 07:00 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: Called and got voicemail

Outgoing call to Vernon Houston
Dec 04, 2023 09:31 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: piling at the moment and expected to go to Feb. Then they will start the dig to 4 basements and will be doing that till June. Stairs in the whole around may as they will try to utilize ramp until they box the whole. Stated to call him mid Jan to further discuss scaff

Outgoing call to Vernon Houston
Aug 17, 2023 05:48 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: Demo just starting. Will be then in the ground for quite a while. Structure wont start until mid next year or so

Quotes

Action Job Name Subject Quote ref number Quote stage Quote Owner Cteated Time Grand Total GP%
The Centennial FSS4687.01 Q1639 Draft Yousif Yousif 2023-09-12T06:01:30+05:30 $1,400,910.00 45