FSS3782 Oct 10, 2023
Jolly Ebong
Closed Time: 2023-10-10T09:36:20+05:30
Status: Completed
Estimating Task Type: Variation - Priority 2
Description: Hi Yousif, Please kindly price 1 x Alloy Stairs going to height as per attached site pictures for 12 weeks. Added to existing scaffold as per attached pictures Alloy for a return bay going outside and around the ladder beams on the front façade. Hi Jolly, Alloy Stair: Erection: $5,760.00+GST (48Hr) Dismantle:$3,840.00+GST (32 Hr) Transport: $600.00+GST Hire: $1,200.00+GST additional bays: Erection: $16,320.00+GST (136 Hr) Dismantle:$10,560.00+GST (88 Hr) Transport: $1,200.00+GST Hire: $3,200.00+GST Yousif