Jobs

Job Name Stage Amount
Open Activities

Open Tasks 0
Open Meetings 0
Open Calls 0

Closed Activities

Closed Tasks 1
Closed Meetings 0
Closed Calls 19

Final Reprice Mar 11, 2020
Yousif Yousif
Closed Time: 2020-03-11T11:22:10+05:30
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


Call scheduled with Jamie Gavin
Apr 09, 2025 01:00 PM
Contact Name:

Status: Completed
Descriptions: Mitch Jefferies is the PM and Peter Baumgart is the CM

Follow Up
Apr 02, 2020 10:37 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: we are not the recommended - we came in 3rd place. He will shed some light once the contract is let. Local contractor got it.

Follow Up
Mar 31, 2020 04:48 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Applied a credit of 1800 and 8 weeks to our price. Explained that's not how we arrive to our price. Went through hire grace. Manual handling. Requirement for a hiab.

Follow Up
Mar 27, 2020 02:30 AM
Michael Eskaros
Contact Name:

Status: Cancelled
Descriptions:

Follow Up
Mar 26, 2020 05:23 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Will give me a call tomorrow to run through it all. We have been shortlisted. WIll discuss tomorrow.

Left a Message
Mar 25, 2020 11:19 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Follow Up
Mar 11, 2020 09:21 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Spoke to Jamie and Arin. Said the email went to junk and we'd reprice right away.

Left a Message
Aug 13, 2019 11:40 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Follow Up
May 28, 2019 11:41 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Went to beach.

Follow Up
May 28, 2019 11:40 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Da delays. Doesnt think he'll be on site till august.

Left a Message
May 28, 2019 05:53 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Left a Message
May 28, 2019 05:53 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Left a Message
May 09, 2019 06:19 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Follow Up
Mar 28, 2019 08:51 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: wanted price for the B class separated. told him $21k. In talks with the client. SOunds promising.

Left a Message
Mar 13, 2019 07:53 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Follow Up
Mar 06, 2019 10:37 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Still a long way off. Design changes are to come later. Thinks this will be months before any decision is made.

Follow Up
Mar 06, 2019 10:18 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Delays with DA. expects something in the next few months. Call back around JUne.

Left a Message
Mar 06, 2019 10:15 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions:

Follow Up
Jan 17, 2019 05:57 AM
Michael Eskaros
Contact Name:

Status: Completed
Descriptions: Won't be starting till March. Scaffold be required after the first fitout so likely April.