Nov 02, 2020 02:30 AM - Nov 02, 2020 04:00 AM
Theo Bardis
Status: Meeting Successfully Completed
Description: This meeting was a safety presentations along with discussing IR with Glenn, Ernest, Frank and their tow heads of safety being Joe and Andrew. Scaff trade to be looked at in the next couple of weeks according to Frank. Scaff not required until June 21

New Meeting
Oct 23, 2020 06:00 AM - Oct 23, 2020 07:30 AM
Theo Bardis
Status: Meeting Successfully Completed
Description: Site meeting along with Yousif. Discussed methodolgy and i- beams as opposed to ladder beams for the openings. Job to be awarded in November.

Meeting Held
Jun 19, 2020 05:30 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: Met with Matt and Frank the P/M. Discussed the project further and attained clarity on a few areas. All quotations will be assessed next week and the week after the list of 5 applicants will be filtered down to 2-3. They will then be called in for an interview to discuss project further. This job is expected to be let within the next 3 or so weeks. Good meeting which went for 2 hours.